This is the current list of trail work identified; tasks without dates have not yet been scheduled
|
Work
|
Date - Time
|
Meeting Place
|
Workers
|
Status
|
Notes
|
River Trail Bridge at Piggery Rd. East side sagging badly at 2 posts with one beam completely off the post. We're going to need to get to this before long, and it ain't gonna be easy...
|
|
|
|
|
reported by Marc, April 3, and confirmed by Kevin, April 17, 2009
|
2 trees down in the Davis corridor, one 18" pine on the trail in from Two Rod, another 10" pine near the intersection of Davis and Link trails.
|
04/18/2009
|
|
George, Henry and Matt
|
Done
|
reported by Kevin, April 16, 2009
|
2 trees down on Two Rod Road, one just south of the Davis corridor junction and the other just south of the Sachs Greenway intersection.
|
|
|
|
Done |
reported by Dejan, Jan 3, 2009
|
|
Trees down on Greenough/redpine trail
one is about 10" diameter - all pines
|
|
|
|
|
Reported by Henry/
3 December
|
| Remove fence posts in GMNWR |
04/01/2007 - 08:00am |
O'Rourke Barn |
Trail Committee |
partial |
ongoing project |
| Remove barbed wire at GMNWR and Greenough border |
04/22/2007 - 08:00am |
Parking by bridge on Maple St. |
Trail Committee |
partial |
ongoing project |
| Install post & TRAIL sign at Bisbee field edge |
|
|
|
|
|
| Install post with blue cross at Cranberry Bog by beaver pile |
|
|
|
|
|
| Install TRAIL sign on tree at Banta Davis at road crossing |
|
|
|
|
|
use salvaged metal posts to tie floating boardwalks in place
|
|
foss/GMWR |
|
|
|
See Work Completed page
Forms and Documents
Upcoming Trail Work
|
|
Tip: To turn text into a link, highlight the text, then click on a page or file from the list above.
|
|
|
Comments (0)
You don't have permission to comment on this page.